Project Update: 5/18/2023
The installation of the drainage system is nearing completion. The contractor has finished construction of the catch basin, and the curb and gutter will be poured beginning May 19. The existing street surface will be removed beginning May 22, 2023.
The contractor will construct ramps between residents' driveways and the street to maintain access for residents. The new paving of the street is scheduled for May 31, 2023. Traffic in and out of the White Stone neighborhood will be restricted during the paving operation. The City is coordinating with the contractor to reduce the amount of time the street will be closed.