Project Update: 5/26/2023
The curb has been poured on the south side of the street, and the cross gutter will be poured on the afternoon of Friday, May 26. The contractor is bringing in the aggregate base material, and they will be grading it May 26, 27, and 30 in preparation for the one-day paving on May 31.
On May 31, White Stone will be closed to traffic. Residents of White Stone who need to get out of the neighborhood will be required to park their cars outside the neighborhood. The contractor has set up a phone line to shuttle residents from their houses to Grapevine Street. Residents may call Erick Vazquez at (760) 895-5020 to request the shuttle service. Upon completion of the paving, the contractor will focus on final items and general cleanup. All work is expected to be complete by June 19.