Presidents' Plaza Parking Lot Renovation

Share Presidents' Plaza Parking Lot Renovation on Facebook Share Presidents' Plaza Parking Lot Renovation on Twitter Share Presidents' Plaza Parking Lot Renovation on Linkedin Email Presidents' Plaza Parking Lot Renovation link

Ribbon-Cutting of Presidents' Plaza, Monday, June, 15, 2022

A valuable community resource made its official debut on Monday, June 13, with the ribbon cutting of the newly refurbished Presidents’ Plaza parking lots. The festivities started at 8 a.m. in the center of Presidents’ Plaza East (between San Luis Rey and Portola avenues). The ceremony began with brief words of welcome before the ribbon-cutting itself. Click play on the video below to watch the ribbon-cutting.


Improvements to Presidents’ Plaza include new pavement, planter areas, modernized trash enclosures with ramps, new striped parking stalls, and enhanced pedestrian walkways. Parking canopies with and without solar are scheduled for installation later this year.


Project Overview

The City of Palm Desert is in the process of significant improvements to the Presidents' Plaza East and West Parking Lots. These aging, heavily used lots serve businesses and their patrons on El Paseo, Highway 111, and adjacent frontage roads between Larkspur Lane and Portola Avenue. The improvements include new asphalt pavement, underground utility upgrades, planter areas, modernization of the trash enclosures, new striped parking stalls, and enhanced ADA-compliant pedestrian walkways.

A primary project goal is to keep the community, patrons, employees, and business owners informed throughout the project's life. This page will be updated regularly with construction updates, interesting project facts, and important notices. Weekly updates complete with maps showing areas of expected construction activity can be found on the project's website.


Patrons and Business Owners

Businesses will remain open throughout project construction and will be accessible during construction. Directional signage and traffic control devices are in place around the site for your safety. Your continued support and patronage of the many businesses that utilize these parking lots are appreciated.

Courtesy Cartscatch a free ride on el paseo

Typically, two courtesy carts circulate on El Paseo from 11:00 a.m. to 6:00 p.m. A third cart has been added into the rotation and will focus on the streets around Presidents’ Plaza and within the parking lots themselves. Courtesy carts will pick up patrons at The Gardens on El Paseo at 15-minute intervals and can be dropped off at their desired location. Hours of operation have been expanded to service Presidents’ Plaza from 11:00 a.m. to 9:00 p.m.

Temporary Parking Locations

Signage has been created to encourage patrons to park at the Gardens and to take a courtesy cart shuttle to their destination. City staff is also working on finalizing short-term parking agreements for the use of nearby parking lots (Union Bank at El Paseo and San Luis Rey and U.S. Bank at El Paseo and Portola) that Presidents Plaza businesses can use through the end of January for employee or valet parking.

Project Delays

The initial construction schedule projected completion by January 2022. During construction, the contractor unexpectedly encountered 14 previously unknown septic tanks. In addition, the contractor has encountered various existing private utilities in conflict with the planned construction, which must each be adjustedThese unforeseen challenges have contributed to delays in the construction schedule.  

The Coachella Valley Water District (CVWD) began installing major upgrades in mid-November but has encountered challenges procuring necessary components such as specific valves and fire equipment for both lots due to ongoing supply chain issues. 

Safety Priority

Please keep a lookout for our caution tape and delineators, and do not enter these areas. These spaces are subject to change due to work conditions or additional areas that may be needed to place work materials. The safety of the public, construction workers, and City staff is our number one priority. Project cones and traffic control devices will be placed in both parking lots. Please follow all signage for your safety and for that of others in the area.


For additional information on this project call the toll-free hotline at 844-226-2220. Residents, business owners, and other interested parties may also sign up for email updates by texting PRESIDENTS to 22828.


business are open during construction


Ribbon-Cutting of Presidents' Plaza, Monday, June, 15, 2022

A valuable community resource made its official debut on Monday, June 13, with the ribbon cutting of the newly refurbished Presidents’ Plaza parking lots. The festivities started at 8 a.m. in the center of Presidents’ Plaza East (between San Luis Rey and Portola avenues). The ceremony began with brief words of welcome before the ribbon-cutting itself. Click play on the video below to watch the ribbon-cutting.


Improvements to Presidents’ Plaza include new pavement, planter areas, modernized trash enclosures with ramps, new striped parking stalls, and enhanced pedestrian walkways. Parking canopies with and without solar are scheduled for installation later this year.


Project Overview

The City of Palm Desert is in the process of significant improvements to the Presidents' Plaza East and West Parking Lots. These aging, heavily used lots serve businesses and their patrons on El Paseo, Highway 111, and adjacent frontage roads between Larkspur Lane and Portola Avenue. The improvements include new asphalt pavement, underground utility upgrades, planter areas, modernization of the trash enclosures, new striped parking stalls, and enhanced ADA-compliant pedestrian walkways.

A primary project goal is to keep the community, patrons, employees, and business owners informed throughout the project's life. This page will be updated regularly with construction updates, interesting project facts, and important notices. Weekly updates complete with maps showing areas of expected construction activity can be found on the project's website.


Patrons and Business Owners

Businesses will remain open throughout project construction and will be accessible during construction. Directional signage and traffic control devices are in place around the site for your safety. Your continued support and patronage of the many businesses that utilize these parking lots are appreciated.

Courtesy Cartscatch a free ride on el paseo

Typically, two courtesy carts circulate on El Paseo from 11:00 a.m. to 6:00 p.m. A third cart has been added into the rotation and will focus on the streets around Presidents’ Plaza and within the parking lots themselves. Courtesy carts will pick up patrons at The Gardens on El Paseo at 15-minute intervals and can be dropped off at their desired location. Hours of operation have been expanded to service Presidents’ Plaza from 11:00 a.m. to 9:00 p.m.

Temporary Parking Locations

Signage has been created to encourage patrons to park at the Gardens and to take a courtesy cart shuttle to their destination. City staff is also working on finalizing short-term parking agreements for the use of nearby parking lots (Union Bank at El Paseo and San Luis Rey and U.S. Bank at El Paseo and Portola) that Presidents Plaza businesses can use through the end of January for employee or valet parking.

Project Delays

The initial construction schedule projected completion by January 2022. During construction, the contractor unexpectedly encountered 14 previously unknown septic tanks. In addition, the contractor has encountered various existing private utilities in conflict with the planned construction, which must each be adjustedThese unforeseen challenges have contributed to delays in the construction schedule.  

The Coachella Valley Water District (CVWD) began installing major upgrades in mid-November but has encountered challenges procuring necessary components such as specific valves and fire equipment for both lots due to ongoing supply chain issues. 

Safety Priority

Please keep a lookout for our caution tape and delineators, and do not enter these areas. These spaces are subject to change due to work conditions or additional areas that may be needed to place work materials. The safety of the public, construction workers, and City staff is our number one priority. Project cones and traffic control devices will be placed in both parking lots. Please follow all signage for your safety and for that of others in the area.


For additional information on this project call the toll-free hotline at 844-226-2220. Residents, business owners, and other interested parties may also sign up for email updates by texting PRESIDENTS to 22828.


business are open during construction


  • Additional West Lot Parking Options

    Share Additional West Lot Parking Options on Facebook Share Additional West Lot Parking Options on Twitter Share Additional West Lot Parking Options on Linkedin Email Additional West Lot Parking Options link

    additional west lot parking options

  • Water Utility Updates

    Share Water Utility Updates on Facebook Share Water Utility Updates on Twitter Share Water Utility Updates on Linkedin Email Water Utility Updates link
    supporting image

    Businesses in the East Lot closest to Portola Avenue were connected to the new water infrastructure last week.

    CVWD is installing new infrastructure on San Luis Rey and the remaining businesses will be connected to the new water lines this week!

    The construction crew is installing the final connections to buildings and pouring missing sidewalk segments as the work is completed!

  • Schedule Update!

    Share Schedule Update! on Facebook Share Schedule Update! on Twitter Share Schedule Update! on Linkedin Email Schedule Update! link

    The initial construction schedule projected completion by January 2022. During construction, the contractor encountered 14 septic tanks and cesspools not previously known. In addition, the contractor has encountered various existing private utilities in conflict with the planned construction, which has to be adjusted. These unknown conflicts have contributed to delays in the construction schedule.

    In addition, the team has coordinated with the Coachella Valley Water District (CVWD) and Southern California Edison (SCE) to install major upgrades to the drinking water and underground electrical systems. SCE will complete their work in early December 2021. CVWD began their work November 16 (night) in the east but has encountered supply chain issues, which has caused delayed completion of their work. At this time, CVWD is not able to provide a schedule for completion due to supply chain issues.

    The project team is working on paving options for the east parking and the southern portion of the west parking lot in late December followed by the west parking lot.

    Following the paving, work will continue with the remaining construction items, including landscaping, carports, trash enclosures, lighting, and final elements of the project until the project completion planned for February.

    The project team thanks you for your continued support as we continue to improve the parking lots.

  • Progress This Week!

    Share Progress This Week! on Facebook Share Progress This Week! on Twitter Share Progress This Week! on Linkedin Email Progress This Week! link
    supporting image

    Concrete placement in new ADA ramps in both parking lots.

    SCE continues their work in the East parking lot.

  • Highlight Last Week

    Share Highlight Last Week on Facebook Share Highlight Last Week on Twitter Share Highlight Last Week on Linkedin Email Highlight Last Week link
    supporting image

    Teamwork at its finest! The construction team, contractor and SCE work together in the field to resolve a utility conflict.

  • Access to East Lot Reopened on Portola Avenue

    Share Access to East Lot Reopened on Portola Avenue on Facebook Share Access to East Lot Reopened on Portola Avenue on Twitter Share Access to East Lot Reopened on Portola Avenue on Linkedin Email Access to East Lot Reopened on Portola Avenue link
    supporting image

    Vehicles access is available at both ends of the parking lot.

  • Weekly Construction Snapshot

    Share Weekly Construction Snapshot on Facebook Share Weekly Construction Snapshot on Twitter Share Weekly Construction Snapshot on Linkedin Email Weekly Construction Snapshot link
    supporting image

    This week, CVWD’s contractor started working on their lines. Progress continues in both parking lots and new ADA ramps.

  • Happy Veteran's Day

    Share Happy Veteran's Day on Facebook Share Happy Veteran's Day on Twitter Share Happy Veteran's Day on Linkedin Email Happy Veteran's Day link
    supporting image

    From Presidents’ Plaza Team, Happy Veterans Day!

    The contractor will work today and no work will be scheduled on Friday, November 12.


  • Construction Look-Ahead - Nov. 8-12

    Share Construction Look-Ahead - Nov. 8-12 on Facebook Share Construction Look-Ahead - Nov. 8-12 on Twitter Share Construction Look-Ahead - Nov. 8-12 on Linkedin Email Construction Look-Ahead - Nov. 8-12 link
    supporting image

    Grading continues on the south side of the West parking lot.

    Installation of ADA-compliant sidewalk and ramps continues in the East Lot.

    SCE will continue work in the East Lot. Look out for their temporary restrictions.

  • Weekly Construction Snapshot

    Share Weekly Construction Snapshot on Facebook Share Weekly Construction Snapshot on Twitter Share Weekly Construction Snapshot on Linkedin Email Weekly Construction Snapshot link
    supporting image

    Crews have moved ahead with subgrade in the south side of the West Lot and continued constructing the new ADA accessible building ramps in the south side of the East Lot. SCE began utility improvements in the East Lot this week.