Palm Desert Aquatic Center Filter & Pump House Replacement Project
Update, September 16: Lap Pool Closure
The Palm Desert Aquatic Center (PDAC) has temporarily closed its lap pool due to ongoing issues with the facility’s filtration system, while weekend recreation swim and the recreation and splash pools remain open. To provide a permanent solution, construction to replace the filter system will begin on November 17, 2025, requiring a full facility closure through January 2026. The project will install new filtration systems, pumps, and heaters for all three pools, ensuring improved reliability and water quality. For schedule updates, visit PDPool.com.
Update, September 9: Lap Pool Closed
The Aquatic Center has experienced intermittent lap pool closures due to high seasonal demand, extreme temperatures, and aging filtration equipment. While a full system replacement is planned for this fall, staff have implemented temporary filtration and maintenance measures to help manage water clarity.
- Lap Pool Closure: September 9th – 14th
Rainchecks will be provided if inclement weather occurs during your visit.
For questions or additional information, please contact the Palm Desert Aquatic Center at 760-565-7467.
Pump Room Renovation Project:
The pump room renovation project was initiated in 2024 due to aging equipment needed to operate the three pools at the Palm Desert Aquatic Center. The facility’s pumps, heaters, and filter tanks are all part of the aquatic center’s original construction, completed in 2011. In that time, the existing equipment has become degraded through use. In addition, new technologies have been developed that allow more energy-efficient operation of the swimming pools.
Following a public bid solicitation process, the City contracted Rogers, Stringer & McClelland, Inc. (RSM, Inc.) to design improvements to the Palm Desert Aquatic Center pump room. The scope of work for the project includes professional engineering and design services for project management, alternatives analysis development, preliminary engineering, aquatic, facility, and hardscape design, engineering design, and bidding support and construction engineering for:
Renovation of the pump room to include the following:
- Remove and replace (3) pool filtration systems
- Remove (5) and replace with (4) pool heaters
- Reconfigure pump room to accommodate new equipment and optimize space
Since the contract initiation, RSM, Inc. provided a conceptual design of the renovation plans in December 2024 with an accompanying narrative providing insight into the design principles that guided the development of the project up to that point. In January 2024, City, YMCA, and RSM, Inc. staff met to discuss the project and review design development plans. With the completion of the final construction plans, RSM, Inc. is working with the Riverside County Health Department to receive plan approval.
City staff are developing a bid package that will be advertised on the City’s online bidding portal, OpenGov, in July 2025. A construction contract will be awarded to the lowest responsive bidder in September 2025. In addition, a quote for the new equipment is being provided for City Council approval at the upcoming August 28, 2025, City Council meeting. The equipment needed to complete the project has an 8- to 10-week lead time. This schedule allows the contractor to begin work as soon as possible, with equipment provided by the City. A full-facility closure is planned in November 2025, with the Aquatic Center being reopened in early 2026.